Question: Suppose that in a binary programming model for project selections, there are a total of five projects available for selection. Write the following constraint in
Suppose that in a binary programming model for project selections, there are a total of five projects available for selection. Write the following constraint in the standard form:
"If projects 2 and 3 are selected, then project 5 cannot be selected."
A.X5 X2 + X3
B.X5 X2 + X3
C.X2 + X3 + X5 2
D.X2 + X3 - X5 3
E.X2 + X3 + X5 2