Question: Suppose that PERT is used to develop a schedule for a project with eight activities, labeled A through H. It is found that the critical
Suppose that PERT is used to develop a schedule for a project with eight activities, labeled A through H. It is found that the critical activities are A, B, D, G, and H. The expected project completion time E[T] is 39.250 weeks. Var(T), the variance of the project duration, is 4.667 weeks2.
What process was used to compute Var(T), the variance of the project duration?
| A. | By taking the square root of E[T] | |
| B. | By adding the variances of the activities NOT on the critical path (C, E, and F) | |
| C. | By adding the variances of all activities in the project | |
| D. | By adding the variances of the activities along the critical path (A, B, D, G, and H) |