Question: Suppose that PERT is used to develop a schedule for a project with eight activities, labeled A through H. It is found that the critical

Suppose that PERT is used to develop a schedule for a project with eight activities, labeled A through H. It is found that the critical activities are A, B, D, G, and H. The expected project completion time E[T] is 39.250 weeks. Var(T), the variance of the project duration, is 4.667 weeks2.

What process was used to compute Var(T), the variance of the project duration?

A.

By taking the square root of E[T]

B.

By adding the variances of the activities NOT on the critical path (C, E, and F)

C.

By adding the variances of all activities in the project

D.

By adding the variances of the activities along the critical path (A, B, D, G, and H)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!