Question: Suppose that resources are specific, i.e. each task requires one particular resource, as indicated in the following table: How will these resource constraints affect the

Suppose that resources are specific, i.e. each task requires one particular resource, as indicated in the following table:

Suppose that resources are specific, i.e. each

How will these resource constraints affect the schedule? How many days will you need to complete the project with these resource constraints in place?

Task u NN Predecessor Duration Resource 2 Kyle 4 Kathy A 3 Kathy B 2 Erin B 5 Erin C 4 Kathy D 4 E,F 6 Erin GH 2 Sam - IOOOO Sam NO