Question: Suppose that resources are specific, i.e. each task requires one particular resource, as indicated in the following table: How will these resource constraints affect the
Suppose that resources are specific, i.e. each task requires one particular resource, as indicated in the following table:

How will these resource constraints affect the schedule? How many days will you need to complete the project with these resource constraints in place?
Task u NN Predecessor Duration Resource 2 Kyle 4 Kathy A 3 Kathy B 2 Erin B 5 Erin C 4 Kathy D 4 E,F 6 Erin GH 2 Sam - IOOOO Sam NOStep by Step Solution