Question: . Suppose that the time to complete activities B , C , and G for the above network is variable, but that for the remaining

. Suppose that the time to complete activities B, C, and G for the above network is
variable, but that for the remaining activities is not variable. Under the assumption
that an activity time has a beta distribution, the path duration times are independent,
the three time estimates (in weeks) are:
Activity Optimistic
time
Most likely
time
Pessimistic
time
B 2412
C 2810
G 258
What is the probability that the project (without crashing) will be completed within
18 weeks or less?