Question: . Suppose that the time to complete activities B , C , and G for the above network is variable, but that for the remaining
Suppose that the time to complete activities B C and G for the above network is
variable, but that for the remaining activities is not variable. Under the assumption
that an activity time has a beta distribution, the path duration times are independent,
the three time estimates in weeks are:
Activity Optimistic
time
Most likely
time
Pessimistic
time
B
C
G
What is the probability that the project without crashing will be completed within
weeks or less?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
