Question: Suppose that when you are formulating a Master Production Schedule, for week t you have the following information: POH t-1 = 299 Forecast t =
Suppose that when you are formulating a Master Production Schedule, for week t you have the following information:
POHt-1 = 299
Forecastt = 133
Bookedt= 140
Assuming nothing is done, what will be POHt?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts