Question: Suppose that when you are formulating a Master Production Schedule, for week t you have the following information: POH t-1 = 255 Forecast t =
Suppose that when you are formulating a Master Production Schedule, for week t you have the following information:
POHt-1 = 255
Forecastt = 141
Bookedt= 133
Assuming nothing is done, what will be POHt?