Question: Suppose there is a 12 step task (index 0 = Start, index 13 = Finish) whose duration of steps and dependencies are given by the

Suppose there is a 12 step task (index 0 = Start, index 13 = Finish) whose duration of steps and dependencies are given by the graph in . Find the minimum time to completion of this task.

3 3 V11 v8 V5 V2 6. 8 V13 V12 V4 V1

V10 V6 V3 What is the minimum time to completion?

3 3 V11 v8 V5 V2 6. 8 V13 V12 V4 V1 V10 V6 V3 What is the minimum time to completion?

Step by Step Solution

3.46 Rating (166 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Answer Activity Dependency Time Start End 1 5 0 5 2 3 0 3 ... View full answer