Question: Suppose we are formulating a Master Production Schedule (MPS) for an item. Week O projected on- hand is 76 units. The lot-size policy for
Suppose we are formulating a Master Production Schedule (MPS) for an item. Week O projected on- hand is 76 units. The lot-size policy for this item calls for L4L ordering. Lead time for this item is one week. There are no safety stock requirements. Here are the demand forecast and the booked orders for this item ... Week 1 Forecast 60 Booked 64 2 3 45 47 45 30 4 45 10 0 5 45 6 60 0 What will be the order size of the first MPS Start Quantity that is needed?
Step by Step Solution
3.43 Rating (156 Votes )
There are 3 Steps involved in it
To determine the order size for the first MPS start quantity we need to calculate the net requiremen... View full answer