Question: Construct the network diagram for the project. Also, calculate the EST and LST of the events and mark on the diagram. Activity A B
Construct the network diagram for the project. Also, calculate the EST and LST of the events and mark on the diagram. Activity A B C D E F G H Time (Weeks) a 4 5 1 7 12 9 4 1 m 4 11 7 8 15 12 7 4 b 10 11 13 9 18 15 10 7 Precedence --- A A C,D B,F E,G
Step by Step Solution
3.50 Rating (153 Votes )
There are 3 Steps involved in it
Answer To construct the network diagram for the project well represent each activity as a node and c... View full answer
Get step-by-step solutions from verified subject matter experts