Question: Suppose we are using the CPM with three time estimates ( PERT ) to schedule a project. What is the variance of the length of
Suppose we are using the CPM with three time estimates PERT to schedule a project. What is the variance of the length of the critical path, if there is a probability that the project will be completed within the expected duration plus three time periods? Select the nearest correct answer. HINT: Use the formula to find the value
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
