Question: Suppose we are using the CPM with three time estimates ( PERT ) to schedule a project. What is the variance of the length of

Suppose we are using the CPM with three time estimates (PERT) to schedule a project. What is the variance of the length of the critical path, if there is a 92.22% probability that the project will be completed within the expected duration plus three time periods? Select the nearest correct answer. (HINT: Use the Z formula to find the value)
1.67
2.34
2.96
3.19
4.46