Question: Suppose we are using the CPM with three time estimates (PERT) to schedule a project. What is the variance of the length of the critical
Suppose we are using the CPM with three time estimates (PERT) to schedule a project. What is the variance of the length of the critical path, if there is a 92.22% probability that the project will be completed within the expected duration plus three time periods? Select the nearest correct answer.
1.67
2.34
2.96
3.19
4.46