Question: Suppose we have a school building project. The target completion date is earlier than the estimated project duration by 3 weeks. The * total slack

Suppose we have a school building project. The

Suppose we have a school building project. The target completion date is earlier than the estimated project duration by 3 weeks. The * total slack in the critical path is equal (2 points) Zero Can't be determined O 6 weeks o -3 weeks o