Question: Suppose we have a school building project. The target completion date is earlier than the estimated project duration by 3 weeks. The total slack in

Suppose we have a school building project. The
Suppose we have a school building project. The target completion date is earlier than the estimated project duration by 3 weeks. The total slack in the critical path is equal (2 points) * O-3 weeks O Can't be determined O 6 weeks O Zero