Question: Suppose we have the following activity list that includes information on immediate predecessors along activity completion times ( in weeks ) under optimistic, normal, and

Suppose we have the following activity list that includes information on immediate predecessors along activity completion times (in weeks) under optimistic, normal, and pessimistic scenarios:
Immediate
Activities Predecessor Optimistic Normal Pessimistic
A ---1711
B ---3810
C A,B 111
Using this information and based solely on the critical path, what is the probability that this project will be completed in 10 weeks or less?
Question 10 options:
0.9015
0.9546
0.50
0.8977