Question: Suppose we have the following activity list that includes information on immediate predecessors along activity completion times ( in weeks ) under optimistic, normal, and

Suppose we have the following activity list that includes information on immediate predecessors along activity completion times (in weeks) under optimistic, normal, and pessimistic scenarios:
Immediate
Activities Predecessor Optimistic Normal Pessimistic
A ---1711
B ---3810
C A,B 111
Using this information, what is the variance of Activity B?
Question 8 options:
0
1.36
2.78
1.00

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!