Question: Suppose we have the following project: Activity D , duration = 3 8 days Activity E , duration = 4 7 days Activity F ,

Suppose we have the following project:
Activity D, duration =38 days
Activity E, duration =47 days
Activity F, duration =34 days
Activity G, duration =40 days
Activity H, duration =15 days
Activity K, duration =11 days
Activity A, duration =13 days
Activity B, duration =27 days
Activity C, duration =17 days
The earliest finish time of activity A is a the end of day