Question: Consider the following project: Activity A , Duration 3 , Predecessor None Activity B , Duration 6 days, Predecessor A Activity C , Duration 3

Consider the following project:
Activity A, Duration 3, Predecessor None
Activity B, Duration 6 days, Predecessor A
Activity C, Duration 3 days, Predecessor A
Activity D, Duration 3 days, Predecessors B, C
Activity E, Duration 4 days, Predecessor D
Activity F, Duration 6 days, Predecessor D
Which of the following activities would not to shorten the project calendar length by crashing?
Question 7Select one:
a.
B
b.
D
c.
None of these answers is correct
d.
C
e.
A