Question: Suppose you evaluated the best-case, most likely, and worst-case duration estimates for an activity and you determined that they were 4 days, 10 days, and
Suppose you evaluated the best-case, most likely, and worst-case duration estimates for an activity and you determined that they were 4 days, 10 days, and 22 days, respectively. Using PERT estimation