Question: Choose the most appropriate answer from listed options (a, b, c or d), and provide an explanation so that your answer is recognized as complete.
Choose the most appropriate answer from listed options (a, b, c or d), and provide an explanation so that your answer is recognized as complete.
9. One of the following statements is false:
a. A Resources Breakdown Structure is a hierarchy structure that identifies process resource base on category and type
b. Duration and effort are synonymous terms
c. A three-point estimate include an optimize, most likely and pessimist estimation
d. A Gantt-chart is a common tools for displays project schedule milestone
10. All of the following are elements in the defining of a project, except:
a. A project is time-limited
b. A project is composed of unrelated activities
c. A project is unique
d. A project is undertaken for a purpose
11. Which of the following circumstances would require the creation of a lag relationship in a network diagram?
a. The critical path
b. The insertion of a dummy variables into a network design
c. A delay after painting a room to allow for the paint to dry before beginning to carpet the room floor
d. An early finish relationship between two activities
12. Suppose you evaluated the best-case, most likely and worse-case duration estimate for an ICT project activity in the campus, and determined that they were 3 days, 4 days and 8 days respectively. Using PERT estimate, be expected duration for the activity:
a. 8 days
b. 5 days
c. 4.5 days
d. 4 days