Question: Swazzi requires that a PERT network be created for each project. This is a flowchart that demonstrates the sequence of activities that must be followed
Swazzi requires that a PERT network be created for each project. This is a flowchart that demonstrates the sequence of activities that must be followed to complete the project. It identifies which tasks must be completed before other tasks.
The previous manager created a PERT network flowchart of all the tasks required to complete the project. Based on the information provided by the division heads in your department, how would you evaluate this flowchart?
Image of PERT network
Event Description
A
Create outline
B
Create product design
C
Create content
D
Code the application
E
Create graphics
F
Enter content into application
G
Quality assurance
Select an option from the choices below and click Submit.
This flowchart is flawed in that an early step is dependent on the completion of a later step.
This flowchart is flawed in that two of the steps are being performed simultaneously even though one of them depends on the completion of the other.
This flowchart adequately represents the needs of the schedule.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer