Question: Swimming Pool Installation: You are the project manager working for Mack's Pool Co . Your project consists of installing a new swimming pool at the

Swimming Pool Installation:
You are the project manager working for Mack's Pool Co. Your project consists of installing a new swimming pool at the local country club before Memorial Day weekend (pool opening weekend). You would like to find the minimum cost schedule for your project. There is a $9,000 per week penalty for each week the project is delayed beyond week 9. In addition, your project team determined that indirect costs are $15,000 per week.
\table[[ACTIVITY,\table[[Immediate],[Predecsor],[(s)]],\table[[NORMAL TIME],[(NT)]],\table[[CRASH],[TIME (CT)]],\table[[Normal Cost],[(NC)]],\table[[Crash (],[(CC]]],[A,--,2,1,7,000,10,0 C],[B,-,2,2,3,000,3,00],[C,A,3,1,12,000,40,0 C],[D,B,3,2,12,000,28,0 C],[E,C,1,1,8,000,8,00],[F,D, E,5,3,5,000,15,0 C],[G,E,3,2,9,000,18,0 C]]
Before crashing, the project duration is week(s).
 Swimming Pool Installation: You are the project manager working for Mack's

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!