Question: System documentation cannot end until three days after testing has started. This is an example of which kind of lag? Start to Start Start to
System documentation cannot end until three days after testing has started. This is an example of which kind of lag?
Start to Start
Start to Finish
Finish to Finish
Finish to Start
Any of these could be correct
Question points
Listen
Activities that must immediately follow a given activity are called activities.
predecessor
successor
prior
immediate
concurrent or parallel