Question: T 0 = 97 sec, W 0 = 4.04 items, CT bot = 24 sec/item, and WIP = 5 items. What is the expected lead-time

T0 = 97 sec, W0 = 4.04 items, CTbot = 24 sec/item, and WIP = 5 items. What is the expected lead-time (LT) in seconds? Enter a whole number.