Question: t o t ml t p t e A-----135 BA222 CA111 DB000 EC,D 234 FC,D 111 GF111 HE, G111 1) Construct a PERT network. [NOTE:

to tml tp te

A-----135

BA222

CA111

DB000

EC,D 234

FC,D 111

GF111

HE, G111

1) Construct a PERT network.

[NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.]

2) By using ES, EF, LF, LS, find the slack of each activity and the critical path.

3) Find the completion time and the standard deviation () for the project round off the standard deviation to the nearest hundredth:twodecimal places.

4) What is the likelihood of this project being completed earlier than6days?

5) Between7and9days?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!