Question: Table 1 0 . 1 0 A work center has the following six jobs waiting to be processed ( all times are shown in days

Table 10.10
A work center has the following six jobs waiting to be processed (all times are shown in days):
\table[[Job,\table[[Time Since],[Arrival]],Process Time,Due Date],[A,10,8,24],[B,7,2,11],[C,5,6,31],[D,3,12,25],[E,1,7,8]]
Use the information in Table 10.10. Which job will be the first one completed if scheduling is done using the first-come, first-served (FCFS) rule?
A
B
C
D