Question: Table 1 1 - 7 A project manager calculated early and late start and finish times for all activities in her eight - activity project
Table
A project manager calculated early and late start and finish times for all activities in her eightactivity project but spilled her energy drink on the paper and the acid in the beverage wiped out some of the table entries. The remaining legible entries are correct.
tableActivityPredecessor,Duration,ESEFLSLFSlackABACADBECFDEGEHFG
Consider the project summarized in Table Provide all missing information.