Table 11-7
A project manager calculated early and late start and finish times for all activities in her eight-activity project but spilled her energy drink on the paper and the acid in the beverage wiped out some of the table entries. The remaining legible entries are correct.
\table[[Activity,Predecessor,Duration,ES,EF,LS,LF,Slack],[A,--,,,,,,],[B,A,,,12,12,,],[C,A,,5,,,18,],[D,B,8,,,,,],[E,C,9,,,,,0],[F,D,E,,27,,,34,0],[G,E,6,,33,,,1],[H,F,G,,34,,,40,]]
Consider the project summarized in Table 11-7. Provide all missing information.
Table 1 1 - 7 A project manager calculated early

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!