Question: Table 11-7 A project manager calculated early and late start and finish times for all activities in her eight-activity project but spilled her energy drink

Table 11-7 A project manager calculated early and

Table 11-7 A project manager calculated early and late start and finish times for all activities in her eight-activity project but spilled her energy drink on the paper and the acid in the beverage wiped out some of the table entries. The remaining legible entries are correct. Predecessor Duration ES EF LS LF Slack Activity A B 12 12 5 18 D E F A A B D,E E F,G 8 9 27 34 0 0 1 G 6 33 H 34 40 3) Consider the project summarized in Table 11-7. Provide all missing information