Table 1: Bernard Holdings Pty Ltd. Activities Activity a m b Predecessor A 17 29 47 None
Fantastic news! We've Found the answer you've been seeking!
Question:
Table 1: Bernard Holdings Pty Ltd. Activities
Activity | a | m | b | Predecessor |
A | 17 | 29 | 47 | None |
B | 6 | 12 | 24 | A |
C | 16 | 19 | 28 | A |
D | 13 | 16 | 19 | B |
E | 2 | 5 | 14 | C |
F | 2 | 5 | 8 | D,E |
- Draw a network diagram for this project and determine: ES, LS, EF, LF, critical path and project duration.
- Determine the probability for this project to be completed before 67 units of time, beyond 60th unit time, and between 60th and 67th unit times.