Question: TABLE 1 : Forecasted demand and working days working days (jan to june)= 22,19,21,21,22,20 TABLE 2 : Costs Inventory holding cost Cost of stockout Cost
TABLE 1: Forecasted demand and working days
working days (jan to june)= 22,19,21,21,22,20
TABLE 2: Costs
| Inventory holding cost Cost of stockout Cost of subcontracting Hiring and training cost Layoff/firing cost Labor hours required Straight-line cost (first 8 hours each day) Overtime cost (time and half) | $1.50/unit/month $5/unit/month $20/unit $200/worker $250/worker 5 hours/unit $4/hour $6/hour |
TABLE 3: Initial inventory and safety stock requirements
| Beginning inventory Safety stock | 400 units 25% of month demand |
NOTE: Straight-line production cost = regular-time (8 hours each day) production cost.
| Table 4: Aggregate Production Planning Requirements | ||||||
| January | February | March | April | May | June | |
| Beginning inventory | 400 | 450 | 375 | 275 | 225 | 275 |
| Demand forecast | 1800 | 1,500 | 1,100 | 900 | 1,100 | 1,600 |
| Safety stock (.25 x Demand forecast) | 450 | 375 | 275 | 225 | 275 | 400 |
| Production requirement (Demand forecast + Safety stock - Beginning inventory) | 1850 | 1425 | 1000 | 850 | 1150 | 1725 |
| Ending inventory (Beginning inventory + Production requirement - Demand forecast) | 450 | 375 | 275 | 225 | 275 | 400 |
PLAN 2: Level Strategy with constant workforce level. Produce to meet forecasted demand over the next six months by maintaining a constant workforce. What is the minimum number of workers needed in this case? For this plan, assume that the available workforce at the start of January is equal to the minimum number of workers needed for this plan (to be determined). In other words, there will be no hiring and firing for this plan.
NOTE 2: In this plan, inventory is allowed to accumulate, with shortages (stockouts) filled from next months production by back ordering. Since XYZ carries a safety stock in each month (refer to Table 4), the inventory costs in each month are calculated based on the units excess (Ending inventory Safety stock) of each month only if this amount is positive.
Use the information given in Tables 1, 2, 3, and 4 to fill in appropriate values for the quantities listed in the first column of the following table (Table 6) for each month (January to June) of the planning period. What is the total cost of production plan 2? (6 marks)
NOTE 3: In solving this aggregate plan, please be sure to give explicit equations/calculations you have used to obtain the number of workers required and the quantities in the first column of TABLE 6 below for the months of January, February and March.: CONSTANT WORKFORCE; VARY INVENTORY AND USE STOCKOUT (IF NECESSARY).
Actual production = actual number of units produced in each month.
| Production Plan level strategy | |||||||
| No. Of Workforce Required | ? | ||||||
| (constant workforce) | |||||||
| Jan | Feb | Mar | Apr | May | Jun | TOTAL | |
| Beg. Inventory | |||||||
| Workng Day Per Month | ? | ||||||
| Production Hour Available | |||||||
| Actual Production | |||||||
| Demand Forecast | |||||||
| Ending Inventory | |||||||
| Shortage Cost | ? | ||||||
| Safety Stock | |||||||
| Units Excess | |||||||
| Inventory Cost | ? | ||||||
| Straight Time Cost | ? | ||||||
| TOTAL | ? | ||||||
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
