Question: Table 1 Project Task Task Identifier Activity (Fill the activities based on your WBS) Predecessor Activity Duration (days) Programmer A - 1 2 B -

Table 1 Project Task

Task Identifier

Activity

(Fill the activities based on your WBS)

Predecessor Activity

Duration (days)

Programmer

A

-

1

2

B

-

2

2

C

A

2

2

D

B

2

2

E

C,D

3

3

F

D,E

2

1

G

F

2

2

a) A risk assessment matrix can help to evaluate and prioritize risks based on the severity of their impact and their likelihood to occur. Determine a relative or numerical scale table for the following risk for your project :

b) Tabulate the risk event on Q4(a) based on the hazard/risk, like hood, impact, detection and risk value.

  1. i.) Technical requirements

  2. ii.) Design

  3. iii.) Quality

  4. iv.) Resources

  5. v.) Testing

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!