Question: Table 1: Projects Activity Description Activity Time Estimate in Weeks (At Best) Time Estimate in Weeks (At Worst) Time Estimate in Weeks (Most Likely Immediate
Table 1: Projects
| Activity Description | Activity | Time Estimate in Weeks (At Best) | Time Estimate in Weeks (At Worst) | Time Estimate in Weeks (Most Likely | Immediate Predecessors |
| Requirements | A | 2 | 4 | 3 | |
| Market Assessments | B | 4 | 10 | 7 | A |
| Design | C | 5 | 9 | 6 | A |
| Development | D | 6 | 16 | 7 | C |
| Testing | E | 7 | 10 | 9 | D |
| Revising | F | 4 | 6 | 5 | B and E |
| Documentation | G | 3 | 10 | 6 | D |
| Quality Assurance | H | 2 | 7 | 4 | C and E |
| Pricing | I | 2 | 2 | 2 | B |
| Installation | J | 3 | 14 | 4 | F, G, H and I |
| Project Handoff | K | 2 | 4 | 3 | J |
Table 2: Crashing Data
| Activity | Crash Time (Weeks) | Normal Costs (S) | Crash Costs ($) |
| A | 3 | 10,000 | 10,000 |
| B | 6 | 20,000 | 25,000 |
| C | 5 | 15,000 | 30,000 |
| D | 6 | 45,000 | 65,000 |
| E | 8 | 10,000 | 20,000 |
| F | 4 | 15,000 | 18,000 |
| G | 4 | 20,000 | 30,000 |
| H | 3 | 10,000 | 15,000 |
| I | 2 | 5,000 | 5,000 |
| J | 5 | 40,000 | 50,000 |
| K | 2 | 15,000 | 25,000 |
Questions
1. What is the duration of the project?
2. Crash the project by 3 weeks.
3. Which activities did you crash?
4. What is the additional cost to crash the project by 3 weeks?