Question: Table 1 represent a project to build a garage for Ms Wendy. Given the following information in table 1, a) Construct a project network of


Table 1 represent a project to build a garage for Ms Wendy. Given the following information in table 1, a) Construct a project network of this project and prescribe all paths are there in this network diagram (15 marks) b) Assess activities represent the Cn'tical Path and interpret to Ms Wendy the early and late activity time needed to complete the project (5 marks) GARAGE PROJECT ID Description Pmdecessor Time A Prepare Site None 2 B Pour Foundation A 3 C Erect Frame B 4 D Roof C 4 E Windows C 1 F Doors C 1 G Electrical C 3 H Rough in Time D.E,F.G 2 l Door Operator D.E,F.G 1 J Paint H.l 2 K Cleaner J 1