Question: Table 10-1 - Earned Value Example (today is day 7) Activity Predecessor Budget, $ % Complete Duration (days) Actual Cost, $ A 3 600 680

Table 10-1 - Earned Value Example (today is day

Table 10-1 - Earned Value Example (today is day 7) Activity Predecessor Budget, $ % Complete Duration (days) Actual Cost, $ A 3 600 680 100 A 2 300 270 100 A 5 800 80 D B 4 400 25 E 2 400 0 a) Draw a network diagram for the project. b) Prepare a baseline budget table using the 50-50 rule. c) In fact, it took 4 days to complete the activity A instead of 3 days. Prepare a status table, showing earned value (BCWP) using the 50-50 rule and Actual Cost (ACWP). d) Plot the earned value (EV) chart including BAC, BCWP, ACWP for the project at day 7

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!