Question: Table 11-2 The following represents a project with four activities. All times are in weeks. Activity Immediate Optimistic Predecessor Time Most Likely Time Pessimistic Time

Table 11-2 The following represents a project

Table 11-2 The following represents a project with four activities. All times are in weeks. Activity Immediate Optimistic Predecessor Time Most Likely Time Pessimistic Time A 8 14 B 8 8 A 6 9 18 D B 5 11 17 According to the data in Table 11-2, what is the critical path? O A-B O A-B-C-D O A-C B-D