Question: Table 1 1 - 2 The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely

Table 11-2
The following represents a project with four activities. All times are in weeks.
Activity Immediate
Predecessor Optimistic
Time Most Likely
Time Pessimistic
Time
A -2814
B -888
C A 6918
D B 51117
According to Table 11-2, there are four activities in the project. Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time. If you wished to find the probability of finishing the project in 20 weeks or fewer, it would be necessary to find the variance and then the standard deviation to be used with the normal distribution. What variance would be used?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!