Question: Table 2 . Cumulative Cash Flow Planned table [ [ Parameter , October' 2 3 , November' 2 3 , December' 2 3 ,

Table 2. Cumulative Cash Flow Planned
\table[[Parameter,October'23,November'23,December'23,January'24,February'24,March'24,April'24,May'24],[BCWS,1,000,2,000,6,000,10,000,18,000,24,000,28,000,30,000]]
Carry out an Earned Value Analysis as of January'17 and calculate;
a) Cost Variance (CV) of the project, as of January'17(2 points)
b) Schedule Variance (SV) of the project, as of January'17(2 points)
c) Cost Performance Index (CPI) of the project, as of January' 17(1 points)
d) Schedule Performance Index (SPI) of the project, as of January' 17(1 points)
e) Estimate the schedule slippage (how many days the project will be delayed) and the new budget estimate at completion (what are the lower and upper limits of the new cost estimate for the project when it is finished).(3 points)
 Table 2. Cumulative Cash Flow Planned \table[[Parameter,October'23,November'23,December'23,January'24,February'24,March'24,April'24,May'24],[BCWS,1,000,2,000,6,000,10,000,18,000,24,000,28,000,30,000]] Carry out an Earned

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!