Question: Table 2 . Cumulative Cash Flow Planned table [ [ Parameter , October' 2 3 , November' 2 3 , December' 2 3 ,
Table Cumulative Cash Flow Planned
tableParameterOctober'November'December'January'February'March'April'May'BCWS
Carry out an Earned Value Analysis as of January' and calculate;
a Cost Variance CV of the project, as of January' points
b Schedule Variance SV of the project, as of January' points
c Cost Performance Index CPI of the project, as of January' points
d Schedule Performance Index SPI of the project, as of January' points
e Estimate the schedule slippage how many days the project will be delayed and the new budget estimate at completion what are the lower and upper limits of the new cost estimate for the project when it is finished points