Question: Table 2 presents project cost and schedule data for a new process installation in a company that manufactures windows and doors. i. ii. 1 2

Table 2 presents project cost and schedule data for a new process installation in a company that manufactures windows and doors. i. ii. 1 2 3 4 5 6 7 8 Calculate the CPI and SPI at days 9 and 12. [20