Question: Table 2 shows the estimated number of programmers needed for the project. Create a resource loading chart for the project. In what months the largest

Table 2 shows the estimated number of programmers needed for the project. Create a resource loading chart for the project. In what months the largest number of programmers is required? In what months the smallest number of programmers is required?Table 2 shows the estimated number of programmers

Activity Table 2: Estimated resource for the project Duration Predecessor Programmers required (in months) (per month 1 2 A B 3 5 4 5 5 2 ALL A B, C D, E 4 4 2 3