Question: Table 3 gives forecasted data about activities, which comprises a project: Table 3 After 8 weeks, activities A , B and C has been completed.

Table 3 gives forecasted data about activities, which comprises a project:
Table 3
After 8 weeks, activities A, B and C has been completed. Table 4 gives the actual project data for this
period.
Table 4
Table 5 gives the forecasted and actual price of resources.
Calculate the following - Budget at Completion, Planned Value, Earned Value, Actual Cost, Cost Variance, Schedule Variance, Cost Performance Index, Estimate to Complete, Estimate at Completion and Variance at Completion.