Question: Table 3 gives forecasted data about activities, which comprises a project: Table 3 After 8 weeks, activities A , B and C has been completed.
Table gives forecasted data about activities, which comprises a project:
Table
After weeks, activities A B and C has been completed. Table gives the actual project data for this
period.
Table
Table gives the forecasted and actual price of resources.
Calculate the following Budget at Completion, Planned Value, Earned Value, Actual Cost, Cost Variance, Schedule Variance, Cost Performance Index, Estimate to Complete, Estimate at Completion and Variance at Completion.