Question: Table 3 Projec tA Projec t B Time 0 -5,000 -3,000 Time 1 3,000 3,000 Time 2 2,000 5,000 Time 3 1,000 10,000 Project
Table 3 Projec tA Projec t B Time 0 -5,000 -3,000 Time 1 3,000 3,000 Time 2 2,000 5,000 Time 3 1,000 10,000 Project A. Project B. Project A and Project B have the same ranking. Cannot calculate a payback period without a discount rate.