Question: TABLE 3 Repair time probabilities utilizing accelerated procedures ( rental crane ) Time Probability 4 days or less 0 . 0 0 1 6 days

TABLE 3 Repair time probabilities utilizing accelerated procedures (rental crane)
Time
Probability
4 days or less
0.001
6 days or less
0.02
8 days or less
0.16
10 days or less
0.50
12 days or less
0.84
14 days or less
0.98
16 days or less
0.999
1. As a maintenance manager, develop a plan of action for the restoration of the failed calciners and present a policy that will be implemented in the future.