Question: Table 7 . 4 Activity Predecessor Time ( weeks ) A - - 6 B - - 6 C A 4 D B 9 E
Table
Activity Predecessor Timeweeks
A
B
C A
D B
E CD
F E
Using Table what is maximum amount of time activity E can be delayed without delaying the normal completion time for the project?
Question Select one:
A
weeks
B
weeks
C
week
D
weeks