Question: Table 7.4 Activity Predecessor Time (weeks) A alml0ln|u|u B D E F C A B C,D E 6 6 4 9 11 Using Table 7.4,

Table 7.4 Activity Predecessor Time (weeks) A alml0ln|u|u B D E F C A B C,D E 6 6 4 9 11 Using Table 7.4, what is the slack for activity A? Select one: O A. two weeks O B. one week OC. five weeks O D. zero weeks
 Table 7.4 Activity Predecessor Time (weeks) A alml0ln|u|u B D E

Table 7.4 Using Table 7.4, what is the slack for activity A? Select one: A. two weeks B. one week C. five weeks D. zero weeks