Question: table [ [ A , , 5 ] , [ B , A , 7 ] , [ C , B , 6 ]
tableABCBDDBBGCJI,
A Draw the precedence activity network using the given table.
B Calculate the earliest and latest start and end dates and the float associated with each activity in the network.
Floats or slack time