Question: table [ [ A , , 5 ] , [ B , A , 7 ] , [ C , B , 6 ]

\table[[A,,5],[B,A,7],[C,B,6],[D,A,5],[E,D,10],[F,B,15],[G,B,8],[H,G,8],[I,C,4],[J,G,4],[K,E,F,5],[L,I,H,3]]
A. Draw the precedence activity network using the given table.
B. Calculate the earliest and latest start and end dates and the float associated with each activity in the network.
Floats or slack time
 \table[[A,,5],[B,A,7],[C,B,6],[D,A,5],[E,D,10],[F,B,15],[G,B,8],[H,G,8],[I,C,4],[J,G,4],[K,E,F,5],[L,I,H,3]] A. Draw the precedence activity network using the given table.