Question: Table A table [ [ Activity , Predecessor,Time ( weeks ) ] , [ A , - - , 8 ] , [ B

Table A
\table[[Activity,Predecessor,Time(weeks)],[A,--,8],[B,A,6],[C,--,4],[D,C,9],[E,A,11],[F,B,3],[G,D, E, F,1]]
Using Table A, what is the earliest completion time for this project?
Multiple Choice
18 weeks
19 weeks
20 weeks
21 weeks
 Table A \table[[Activity,Predecessor,Time(weeks)],[A,--,8],[B,A,6],[C,--,4],[D,C,9],[E,A,11],[F,B,3],[G,D, E, F,1]] Using Table A, what is the