Question: table [ [ Activity , A , B , C , D , E , F , G ] , [ Immediate Predecessors, -

\table[[Activity,A,B,C,D,E,F,G],[Immediate Predecessors,-,-,A,A, B,D,C,E,E],[Expected Time (Weeks),5,7,10,6,7,4,3]]
Calculate the latest finish time for activity E.
a.24
b.20
c.7
d.13
 \table[[Activity,A,B,C,D,E,F,G],[Immediate Predecessors,-,-,A,A, B,D,C,E,E],[Expected Time (Weeks),5,7,10,6,7,4,3]] Calculate the latest finish time for