Question: table [ [ Activity , Activity Time ( days ) , Immediate Predecessor ( s ) ] , [ A , 7 , -

\table[[Activity,Activity Time (days),Immediate Predecessor(s)],[A,7,-],[B,5,A],[C,3,A],[D,3,B, C],[E,5,D],[F,3,E],[G,6,E]]
a. Choose the correct network diagram for this project.
A.
B.
.
c.
D.
b. Determine the critical path and project duration.
The critical path is path and the project duration is days. (Enter your response as an integer.)