Question: table [ [ Activity , ACWP,BCWP , BCWS , CPI,SPI,SV , CV ] , [ A , 6 0 0 , 6 0 0

\table[[Activity,ACWP,BCWP,BCWS,CPI,SPI,SV,CV],[A,600,600,600,,,,],[B,1400,1200,1200,,,,],[C,500,400,800,,,,],[D,200,200,400,,,,],[E,0,0,0,,,,],[\table[[Total],[cost]],2700,2400,3000,,,,]]
Our project is over
Our project is behind schedule
CPI =BCWPACWP,SPI =BCWPBCWS
CV=BCWP-ACWP
SV=BCWP-BCWS