Question: The project started and your immediate supervisor asked for a field report on day 10. The field report you submitted on day 10 is given

The project started and your immediate supervisor asked for a field report on day 10. The field report you submitted on day 10 is given below.

Field Report at Day 10

Activity

Actual Completion %

Cost Incurred

A

100

2400

B

100

1200

C

100

4000

D

80

4000

E

25

4000

F

0

0

Question 3. Calculate the BCWP, BCWS, CPI, SPI, CV, and SV for the field report day 10. Show your calculations, and summarize the results on a table.