Question: The project started and your immediate supervisor asked for a field report on day 10. The field report you submitted on day 10 is given
The project started and your immediate supervisor asked for a field report on day 10. The field report you submitted on day 10 is given below.
| Field Report at Day 10 | ||
| Activity | Actual Completion % | Cost Incurred |
| A | 100 | 2400 |
| B | 100 | 1200 |
| C | 100 | 4000 |
| D | 80 | 4000 |
| E | 25 | 4000 |
| F | 0 | 0 |
Question 3. Calculate the BCWP, BCWS, CPI, SPI, CV, and SV for the field report day 10. Show your calculations, and summarize the results on a table.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
