Question: table [ [ Activity , Description,Predecessor,a opt, m ml , b pess ] , [ 1 , Codify accounts,None, 1 6 , 1 9
tableActivityDescription,Predecessor,a opt, ml pessCodify accounts,None,File articles of unification,None,Unify price and credit policy,None,Unify personnel policies,None,Unify data processing,Train accounting staff,Pilot run data processing,Calculate P & L and balance sheet,Transfer real property,Train salesforce,Negotiate with unions,Determine capital needs,Explain personnel policies,Secure line of credit,End,
Compute the expected time for each activity.
Compute the variance for each activity.
Page
Compute the expected project duration.
What is the probability of completing the project by day Within days?
What is the probability of completing "Negotiate with unions" by day